Latest Update

Nigerian Electricity Regulatory Commission (NERC) has directed the 11 electricity distribution companies (Discos) to stop further collection of electricity bills under the estimated billing system.

Nigerian Electricity Regulatory Commission (NERC) has directed the 11 electricity distribution companies (Discos) to stop further collection of electricity bills under the estimated billing system.
The suspension order signed by NERC’s Chairman, Mr. James Momoh and Commissioner, Legal, Licensing, and Compliance, Mr. Dafe Akpeneye, takes effect from February 20 and has been circulated to all Discos concerned.
The copy of the directive order sighted by Daily Sun titled ‘‘Order on the Capping of Estimated Bills in the Nigerian Electricity Supply Industry (NESI), repeals the methodology for estimated billion regulations 2012 and shall cease to have an effect on the issuance of a new order on the same subject matter by NERC.
NERC directed further that based on the above, the estimated billing methodology is hereby repealed and shall cease to have effect as a basis for computing the consum
Option of unmetered customers in NESI.


Discos shall ensure that all customers on tariff class A1 in their franchise areas are properly identified and metered by 30 April 2020. While all unmetered RS and C1 customers shall not be invoiced for the consumption of energy beyond the cap stipulated in schedule 1 of this order.
All R1 customers, who by definition consume no more than a 50-kilowatt hour(kWh) of energy per month, shall continue to be billed at N4 kWhr and a maximum of N200 per month unless otherwise amended by an order of the commission.
The NERC order instructed further that the energy cap prescribed by the commission shall only apply to R2 and C1 customers, adding that all other customers on higher tariff classes must be metered by Discos no later than April 30, 2020, failing which these customers are not liable to pay any estimated bill issues by Discos
Any customer on such higher tariff classes not metered beyond April 30, 2020, shall remain connected to supply without further payment to the Disco until a meter is installed on the premises under the framework of Meter Asset Provider (MAP) regulations or any other financing arrangement approved by the commission.
Customers whose current estimated bills are lower than the prescribed energy cap shall remain so without any upward adjustment until a meter is installed by the Disco under the MAP regulation or any other initiative approved by the commission.

However, it warned that any customer that rejects the installation of a meter on their premises by a Disco shall not be entitled to supply and must be disconnected by the Disco, and shall only be reconnected to the network with the installation of a meter.
Meanwhile, ahead of the April target for the likely introduction of new electricity tariffs, NERC said it will begin a nationwide consultation with stakeholders.
According to a notice by Momoh, the consultations will hold from February 25 to March 11 in 12 locations nationwide.
He said the NERC has received Extraordinary Tariff Review Applications from the eleven (11) Electricity Distribution Companies (DisCos) and the Transmission Company of Nigeria Plc (TCN).

He said the consultations will hold as follows: Eko Electricity DISCO (February 25); Kaduna (February 25); Abuja (February 26); Ikeja (February 26); and Ibadan, (February 28).